At a glance
- The available remedies depend on the contract, the type of transaction and the law that governs it.
- Document the breach and notify the other party promptly, with enough detail to identify the problem and your position.
- For a sale of goods governed by Finnish law, the Sale of Goods Act provides default remedies. Service contracts are assessed under their terms and general contract principles.
- Damages require a legal basis and proof. Termination is generally reserved for a sufficiently serious breach, subject to the contract and applicable law.
- Check governing-law, dispute-resolution, notice, limitation and liability clauses before taking action.
A breach of contract occurs when a party fails to perform an agreed obligation, such as making a late delivery, supplying defective goods, providing incomplete services or failing to pay.
The remedies depend on the contract, transaction type, any special legislation and governing law. This guide focuses on business-to-business contracts governed by Finnish law. Consumer, employment, lease and other regulated relationships may follow specific rules.
Start with the contract and the applicable law
Read the agreement, schedules, order confirmations and incorporated standard terms. Identify the missed obligation, notice and cure periods, liability limits, contractual penalties, termination rights and dispute forum. Individual orders may have separate terms under a framework agreement.
For a sale of goods, the Finnish Sale of Goods Act (355/1987) supplies default rules when the parties have not agreed otherwise. Many of its provisions are non-mandatory in business-to-business sales, so the contract can change the statutory position. Service contracts do not generally fall under that Act as a whole; their terms and applicable general principles must be considered instead.
For a cross-border contract, check the governing-law and dispute-resolution clauses. Mandatory rules may still matter, and the UN Convention on Contracts for the International Sale of Goods (CISG) may apply to an international sale unless excluded or inapplicable. One Finnish party does not by itself mean Finnish law governs.
Preserve evidence and give a specific notice
Keep the agreement, orders, specifications, delivery records, invoices, test results and correspondence. Record what happened and when, its practical effects, and preserve relevant evidence. Take reasonable steps to prevent further loss.
Notify the other party promptly. Identify the obligation, the facts, when you discovered the issue and the response you seek. Follow the contract’s notice method and deadline. Timing and required detail vary; a vague complaint may not preserve every claim. Where appropriate, request a cure by a clear date and retain proof that notice was delivered.
Possible remedies depend on the breach
There is no mandatory “remedies ladder” that every claimant must follow. Depending on the contract and legal basis, potential responses may include demanding performance, allowing or requiring a cure, seeking repair or replacement, claiming a price reduction, withholding a proportionate part of a reciprocal performance, claiming damages, relying on an agreed contractual penalty or terminating the contract.
These options are not automatic, and some remedies have an order of priority. For defective goods, the Sale of Goods Act generally gives repair or replacement priority over a price reduction or termination, where an appropriate cure is available within a reasonable time. A service customer’s remedies turn on the agreed service, cure provisions and applicable principles. Check for a right to cure before arranging substitute work or rejecting performance.
Withholding your own performance can create risk if unjustified or excessive. Consider the connection between the obligations, the seriousness of the breach and the amount in dispute before withholding payment or work.
Damages require a basis, proof and mitigation
Damages are not automatic. You will generally need a legal basis for liability, proof of loss caused by the breach and evidence of its amount. The test depends on the statute, contract and transaction. Keep records linking each claimed amount to the breach.
In a sale governed by the Sale of Goods Act, the seller may be liable for direct loss from delay or defects unless the statutory exemption applies. Indirect loss generally requires an additional basis, such as negligence; for defective goods, departure from a specific undertaking can also matter. The Act classifies certain production losses, lost third-party profits and damage to other property as indirect loss. Those categories should not be treated as a universal test for service contracts. In other contracts, the agreement may define recoverable loss, exclude categories, cap liability or set different conditions, subject to applicable law and limits on enforcing the clause.
Take reasonable steps to limit avoidable loss, such as finding a substitute or stopping work that would add unnecessary costs. Keep evidence of those steps and unavoidable expenses. Downstream costs, lost profit or customer claims are not automatically recoverable; causation, contract terms and statutory rules matter.
Contractual penalties depend on the clause
A contractual penalty is payable only if the parties agreed to one and the clause covers the breach in question. Read the trigger, amount, calculation method, notice requirements and any cap carefully. A penalty clause is not automatically invalid simply because it resembles a common-law “penalty”; Finnish law and the wording of the agreement govern its effect. A term may be adjusted if it is unreasonable under the applicable rules.
The relationship between a contractual penalty and damages depends on the clause and its interpretation. The agreement may make the penalty the exclusive remedy, allow additional damages, or provide another arrangement. Do not assume that the claimant can always recover both the penalty and the full amount of the same loss. Check the wording for crediting, caps and any requirement to prove loss.
Termination is usually for a serious breach
Ending a contract because of a breach is different from exercising an ordinary right to give notice. Here, termination means ending the contract in response to the breach. The breach will commonly need to be sufficiently serious. Relevant factors include the obligation’s importance, its effect on the contract’s purpose, whether it can be cured, the parties’ conduct and any termination clause. Under the Sale of Goods Act, the seller’s actual or expected awareness of the breach’s significance to the buyer can also matter.
If the contract or law calls for an opportunity to cure, give clear written notice and time to remedy before terminating. The process varies, and some clauses or circumstances may permit termination without a further cure period. State the basis and effective date, and consider any post-termination duties.
Do not treat a missed deadline or a single defect as automatically giving a right to terminate. If termination is later found unjustified, the terminating party may itself be in breach. Get advice before taking that step where the contract is valuable, ongoing or difficult to replace.
Oral agreements and limitation periods
Many business contracts can be oral, though some require a particular form. Proving the terms may be difficult; emails, quotations, order confirmations, notes and the parties’ conduct can help. Do not assume a penalty or liability limit applies unless that term was incorporated into the agreement.
The general limitation period under the Finnish Limitation Act (728/2003) is three years, but the starting point depends on the claim. An agreed payment debt normally runs from its due date. Compensation for defective performance generally runs from when the creditor discovered, or should have discovered, the defect in performance. Other periods and special rules may apply.
Limitation can often be interrupted by a sufficiently specific demand or reminder; a court action is not always needed. A damages demand must identify the basis and amount to the extent reasonably required. A valid interruption normally starts a new period. Negotiations alone may not suffice. A timely notice of breach and interruption of limitation are separate questions: do not assume that one automatically deals with both.
A practical first response
- Find the signed terms, incorporated documents and any governing-law clause.
- Identify the specific obligation, breach, relevant dates and supporting evidence.
- Send a prompt, specific notice using the required method and reserve the remedies supported by the contract and law.
- Assess whether a cure, proportionate withholding, damages claim or termination is justified, and take steps to limit loss.
- Check limitation periods, liability clauses and dispute procedures before deadlines pass.
The right response depends on the contract and the facts. I can help assess a Finnish-law business dispute through dispute resolution services, or review and prepare commercial terms through business contract services. Contacting me does not commit you to engaging my services.
Frequently asked questions
What counts as a breach of contract?
A breach is a failure to perform an obligation under the agreement, such as late delivery, defective goods, incomplete services, non-payment or failure to meet another contractual duty. Whether a particular event is a breach depends on the agreed terms and applicable law.
What can a business claim after a breach?
Depending on the contract and legal basis, possible remedies may include performance, cure, repair or replacement, a price reduction, proportionate withholding, damages, a contractual penalty or termination. No remedy is automatic in every case; check the agreement and the rules governing the transaction.
Can I terminate a contract for one breach?
Sometimes. The breach will generally need to be serious enough under the contract and applicable law. The agreement may also require notice and a chance to cure. Terminating without a sufficient basis can expose your business to a claim, so review the clause and facts first.
Can I claim both a contractual penalty and damages?
It depends on how the penalty clause allocates remedies and how it applies to the loss claimed. The clause may allow additional damages, make the penalty exclusive or provide for another arrangement. Check whether the same loss must be credited or whether a cap applies.
How long do I have to bring a contract claim in Finland?
Many contract claims are subject to a general three-year limitation period under the Limitation Act, but the starting point and interruption rules vary. Special rules may apply. Identify the type of claim and its start date promptly; do not assume one deadline covers every contractual debt.
Sources
- Sale of Goods Act (355/1987), especially sections 1–5, 22–42 and 67–70 (Finlex, Finnish)
- Act on the Limitation of Debts (728/2003), especially sections 4–7 and 10–13 (Finlex, Finnish)
- Contracts Act (228/1929), section 36 on unreasonable terms (Finlex, Finnish)
- UN Convention on Contracts for the International Sale of Goods (CISG): overview and text (UNCITRAL)
Information date: 12 October 2026. This article is general information, not advice on a specific matter.